South Australia
Building and Construction
Industry Security of Payment Act 2009
An
Act to provide for payments for construction work carried out, and related
goods and services supplied, under construction contracts; to make related
amendments to the Building Work Contractors Act 1995 and the Commercial
Arbitration and Industrial Referral Agreements Act 1986; and for other
purposes.
Contents
Part 1—Preliminary
5 Definition
of "construction work"
6 Definition
of "related goods and services"
Part 2—Rights to progress
payments
10 Valuation
of construction work and related goods and services
12 Effect
of "pay when paid" provisions
Part 3—Procedure for
recovering progress payments
Division 1—Payment claims
and payment schedules
15 Consequences
of not paying claimant where no payment schedule
16 Consequences
of not paying claimant in accordance with payment schedule
Division 2—Adjudication of disputes
18 Eligibility
criteria for adjudicators
22 Adjudicator's
determination
23 Respondent
required to pay adjudicated amount
24 Consequences
of not paying claimant adjudicated amount
25 Filing
of adjudication certificate or costs certificate as judgment debt
26 Claimant
may make new application in certain circumstances
26A Claimant
may discontinue adjudication
Division 3—Claimant's right to suspend construction work
Division 4—General
30 Protection
from liability for adjudicators and authorised nominating authorities
31 Effect
of Part on civil proceedings
Part 4—Miscellaneous
34 Regulations
Schedule 1—Related amendment and transitional provision
Part 1—Preliminary
Part 2—Amendment of Building
Work Contractors Act 1995
2 Amendment
of section 30—Payments under or in relation to domestic building work
contracts
Part 3—Amendment of Commercial Arbitration and Industrial
Referral Agreements Act 1986
3 Amendment
of section 3—Application provisions
Part 4—Transitional
provision
The Parliament of South Australia enacts as follows:
This
Act may be cited as the Building and Construction Industry Security of
Payment Act 2009.
This
Act will come into operation on a day to be fixed by proclamation.
(1) The object of this
Act is to ensure that a person who undertakes to carry out construction work (or who undertakes to supply related goods and services) under a construction contract is entitled to receive, and is
able to recover, progress payments in relation to
the carrying out of that work and the supplying of those goods and services.
(2) The means by which
this Act ensures that a person is entitled to receive a progress payment is by
granting a statutory entitlement to such a payment regardless of whether the
relevant construction contract makes provision for progress payments.
(3) The
means by which this Act ensures that a person is able to recover a progress
payment is by establishing a procedure that involves—
(a) the
making of a payment claim by the person claiming
payment; and
(b) the
provision of a payment schedule by the person by
whom the payment is payable; and
(c) the
referral of any disputed claim to an adjudicator for
determination; and
(d) the
payment of the progress payment so determined.
(4) It
is intended that this Act does not limit—
(a) any
other entitlement that a claimant may have under a construction contract; or
(b) any
other remedy that a claimant may have for recovering any such other
entitlement.
In this Act, unless the contrary intention appears—
adjudicated amount means the amount of a progress payment that an adjudicator
determines to be payable, as referred to in section 22;
adjudication application means an application
referred to in section 17;
adjudication certificate means a certificate
provided by an authorised nominating authority under section 24;
adjudication fees means fees or expenses
charged by an authorised nominating authority, or by an adjudicator, under this Act;
adjudication response means a response referred
to in section 20;
adjudicator, in relation to an adjudication
application, means the person appointed in accordance with this Act to
determine the application;
authorised nominating authority means a person authorised by the
Minister under section 28 to nominate persons to
determine adjudication applications;
business day means any day other than—
(a) a
Saturday, Sunday or public holiday; or
(b) 27, 28, 29, 30 or
31 December; or
(c) any
other day on which there is a Statewide shut‑down
of the operations of the building and construction industry;
claimant means person by whom a payment claim is
served under section 13;
claimed amount
means an amount of a progress payment claimed to be
due for construction work carried out, or for related goods and services supplied, as referred to in section 13;
construction contract means a contract or other arrangement under which 1 party
undertakes to carry out construction work, or to
supply related goods and services, for another party;
construction work—see section 5;
due date, in relation to a progress payment, means the due date for the progress
payment, as referred to in section 11;
exercise a function includes
perform a duty;
function includes a power,
authority or duty;
payment claim means a claim
referred to in section 13;
payment schedule means a schedule
referred to in section 14;
progress payment means a payment to
which a person is entitled under section 8, and includes (without
affecting any such entitlement)—
(a) the
final payment for construction work carried out
(or for related goods and services supplied) under a construction contract; and
(b) a
single or one‑off payment for carrying out construction work (or for
supplying related goods and services) under a construction contract; and
(c) a
payment that is based on an event or date (known in the building and
construction industry as a "milestone payment");
recognised financial institution means a bank or any other person or body prescribed by the regulations
for the purposes of this definition;
reference date, in relation to a construction contract, means—
(a) a date determined
by or in accordance with the terms of the contract as the date on which a claim
for a progress payment may be made in relation to
work carried out or undertaken to be carried out (or related
goods and services supplied or undertaken to be supplied) under the
contract; or
(b) if the contract
makes no express provision with respect to the matter—the last day of the named
month in which the construction work was first
carried out (or the related goods and services were first supplied) under the
contract and the last day of each subsequent named month;
related goods and services—see section 6;
respondent means a person on whom a payment claim
is served under section 13;
scheduled amount means the amount of a
progress payment that is proposed to be made under a
payment schedule, as referred to in section 14.
5—Definition of "construction work"
(1) In this Act—
construction
work means any of the following work:
(a) the
construction, alteration, repair, restoration, maintenance, extension,
demolition or dismantling of buildings or structures forming, or to form, part
of land (whether permanent or not);
(b) the construction,
alteration, repair, restoration, maintenance, extension, demolition or
dismantling of works forming, or to form, part of land, including walls, roadworks, power‑lines, telecommunication apparatus,
aircraft runways, docks and harbours, railways, inland waterways, pipelines,
reservoirs, water mains, wells, sewers, industrial plant and installations for
purposes of land drainage or coast protection;
(c) the installation in
any building, structure or works of fittings forming, or to form, part of land,
including heating, lighting, air‑conditioning, ventilation, power supply,
drainage, sanitation, water supply, fire protection, security and
communications systems;
(d) the external or
internal cleaning of buildings, structures and works, so far as it is carried
out in the course of their construction, alteration, repair, restoration,
maintenance or extension;
(e) any operation that
forms an integral part of, or is preparatory to or is for rendering complete,
work of the kind referred to in paragraph (a), (b) or (c), including—
(i) site clearance, earth‑moving, excavation, tunnelling
and boring; and
(ii) the
laying of foundations; and
(iii) the
erection, maintenance or dismantling of fences or scaffolding; and
(iv) the
prefabrication of components to form part of any building, structure or works,
whether carried out on‑site or off‑site; and
(v) site
restoration, landscaping and the provision of roadways and other access works;
(f) the
painting or decorating of the internal or external surfaces of any building,
structure or works;
(g) other
work of a kind prescribed by the regulations for the purposes of this
subsection.
(2) Despite subsection (1), construction
work does not include the following work:
(a) the
drilling for, or extraction of, oil or natural gas;
(b) the
extraction (whether by underground or surface working) of minerals, including
tunnelling or boring, or constructing underground works, for that purpose;
(c) other
work of a kind prescribed by the regulations for the purposes of this
subsection.
6—Definition of "related goods and services"
(1) In
this Act—
related
goods and services, in relation to construction
work, means any of the following goods and services:
(a) goods
of the following kind:
(i) materials and components to form part of any building,
structure or work arising from construction work;
(ii) plant
or materials (whether supplied by sale, hire or otherwise) for use in
connection with the carrying out of construction work;
(b) services
of the following kind:
(i) the provision of labour to carry out construction work;
(ii) architectural,
design, surveying or quantity surveying services in relation to construction
work;
(iii) building,
engineering, interior or exterior decoration or landscape advisory or technical
services in relation to construction work;
(c) goods
and services of a kind prescribed by the regulations for the purposes of this
subsection.
(2) Despite
subsection (1), related goods and services does not include
goods or services of a kind prescribed by the regulations for the purposes of
this subsection.
(3) In this Act, a
reference to related goods and services includes a reference to related goods
or services.
(1) Subject to this section,
this Act applies to any construction contract,
whether written or oral, or partly written and partly oral, and so applies even
if the contract is expressed to be governed by the law of a jurisdiction other
than South Australia.
(2) This
Act does not apply to—
(a) a
construction contract that forms part of a loan agreement, a contract of
guarantee or a contract of insurance under which a recognised
financial institution undertakes—
(i) to lend money or to repay money lent; or
(ii) to
guarantee payment of money owing or repayment of money lent; or
(iii) to
provide an indemnity with respect to construction work
carried out, or related goods and services supplied,
under the construction contract; or
(b) a construction
contract for the carrying out of domestic building work (within the meaning of
the Building
Work Contractors Act 1995) on such part of any premises that the
party for whom the work is carried out resides in or proposes to reside in; or
(c) a
construction contract under which it is agreed that the consideration payable
for construction work carried out under the contract, or for related goods and
services supplied under the contract, is to be calculated otherwise than by
reference to the value of the work carried out or the value of the goods and
services supplied.
(3) This
Act does not apply to a construction contract to the extent to which it
contains—
(a) provisions under
which a party undertakes to carry out construction work, or supply related
goods and services, as an employee (within the meaning of the Fair Work
Act 1994) of the party for whom the work is to be carried out or
the related goods and services are to be supplied; or
(ab) provisions under which a party undertakes to
carry out construction work, or to supply related goods and services, as a
condition of a loan agreement with a recognised financial institution; or
(b) provisions
under which a party undertakes—
(i) to lend money or to repay money lent; or
(ii) to
guarantee payment of money owing or repayment of money lent; or
(iii) to
provide an indemnity with respect to construction work carried out, or related
goods and services supplied, under the construction contract.
(4) This
Act does not apply to a construction contract to the extent to which it deals
with—
(a) construction
work carried out outside this State; and
(b) related
goods and services supplied in respect of construction work carried out outside
this State.
(5) This Act does not
apply to a construction contract, or class of construction contracts, prescribed
for the purposes of this section.
Part 2—Rights to progress payments
On and from each reference date under a
construction contract, a person—
(a) who
has undertaken to carry out construction work
under the contract; or
(b) who
has undertaken to supply related goods and services
under the contract,
is entitled to a progress payment.
The amount of a progress payment to
which a person is entitled in respect of a construction
contract is to be—
(a) the
amount calculated in accordance with the terms of the contract; or
(b) if the contract
makes no express provision with respect to the matter—the amount calculated on
the basis of the value of construction work
carried out or undertaken to be carried out by the person (or of related goods and services supplied or undertaken to be
supplied by the person) under the contract.
10—Valuation of construction work and related goods and services
(1) Construction work
carried out under a construction contract is to be
valued—
(a) in
accordance with the terms of the contract; or
(b) if
the contract makes no express provision with respect to the matter, having
regard to—
(i) the contract price for the work; and
(ii) any
other rates or prices set out in the contract; and
(iii) any variation
agreed to by the parties to the contract by which the contract price, or any
other rate or price set out in the contract, is to be adjusted by a specific
amount; and
(iv) if
any of the work is defective, the estimated cost of rectifying the defect.
(2) Related goods and
services supplied or undertaken to be supplied under a construction
contract are to be valued—
(a) in
accordance with the terms of the contract; or
(b) if
the contract makes no express provision with respect to the matter, having
regard to—
(i) the contract price for the goods and services; and
(ii) any
other rates or prices set out in the contract; and
(iii) any variation
agreed to by the parties to the contract by which the contract price, or any
other rate or price set out in the contract, is to be adjusted by a specific
amount; and
(iv) if
any of the goods are defective, the estimated cost of rectifying the defect,
and,
in the case of materials and components that are to form part of any building,
structure or work arising from construction work, on the basis that the only
materials and components to be included in the valuation are those that have
become (or, on payment, will become) the property of the party for whom
construction work is being carried out.
(1) A
progress payment under a construction
contract becomes due and payable—
(a) on
the date on which the payment becomes due and payable in accordance with the
terms of the contract; or
(b) if
the contract makes no express provision with respect to the matter—on the date
occurring 15 business days after a payment claim is made under Part 3
in relation to the payment.
(2) Interest
is payable on the unpaid amount of a progress payment that has become due and
payable at the rate—
(a) prescribed under
the Supreme
Court Act 1935 in respect of judgment debts of the Supreme Court;
or
(b) specified
under the construction contract,
whichever is the greater.
(3) If a progress payment
becomes due and payable, the claimant is entitled to
exercise a lien in respect of the unpaid amount over any unfixed plant or
materials supplied by the claimant for use in connection with the carrying out
of the construction work for the respondent.
(4) A lien or charge
over the unfixed plant or materials existing before the date on which the
progress payment becomes due and payable takes priority over a lien under
subsection (3).
(5) Subsection (3)
does not confer on the claimant any right against a third party who is the
owner of the unfixed plant or materials.
12—Effect of "pay when paid" provisions
(1) A pay when paid
provision of a construction contract has no effect
in relation to any payment for construction work
carried out or undertaken to be carried out (or for related
goods and services supplied or undertaken to be supplied) under the
contract.
(2) In
this section—
money
owing, in relation to a construction contract, means money owing for
construction work carried out or undertaken to be carried out (or for related
goods and services supplied or undertaken to be supplied) under the contract;
pay
when paid provision of a construction contract means a
provision of the contract—
(a) that makes the
liability of 1 party (the first party) to pay money owing to
another party (the second party) contingent on payment to
the first party by a further party (the third party) of
the whole or a part of that money; or
(b) that makes the due
date for payment of money owing by the first party to the second party
dependent on the date on which payment of the whole or a part of that money is
made to the first party by the third party; or
(c) that otherwise
makes the liability to pay money owing, or the due date for payment of money
owing, contingent or dependent on the operation of another contract.
Part 3—Procedure for
recovering progress payments
Division 1—Payment claims
and payment schedules
(1) A person referred to
in section 8 who is or who
claims to be entitled to a progress payment (the claimant)
may serve a payment claim on the person who, under
the contract concerned, is or may be liable to make the payment.
(2) A
payment claim—
(a) must
identify the construction work (or related goods and services) to which the progress
payment relates; and
(b) must
indicate the amount of the progress payment that the claimant
claims to be due (the claimed amount); and
(c) must
state that it is made under this Act.
(3) The
claimed amount may include an amount—
(a) that
the respondent is liable to pay the claimant under section 27(3); or
(b) that
is held under the construction contract by the
respondent and that the claimant claims is due for release.
(4) A
payment claim may be served only within—
(a) the
period determined by or in accordance with the terms of the construction
contract; or
(b) the
period of 6 months after the construction work to which the claim relates
was last carried out (or the related goods and services to which the claim
relates were last supplied),
whichever is the later.
(5) A claimant cannot
serve more than 1 payment claim in respect of each reference
date under the construction contract.
(6) However,
subsection (5) does not prevent the claimant from including in a payment
claim an amount that has been the subject of a previous claim.
(1) A person on whom a payment claim is served (the respondent)
may reply to the claim by providing a payment
schedule to the claimant.
(2) A
payment schedule—
(a) must
identify the payment claim to which it relates; and
(b) must
indicate the amount of the payment (if any) that the respondent
proposes to make (the scheduled amount).
(3) If the scheduled amount is less than the claimed amount, the schedule must indicate why the
scheduled amount is less and (if it is less because the respondent is
withholding payment for any reason) the respondent's reasons for withholding
payment.
(4) If—
(a) a
claimant serves a payment claim on a respondent; and
(b) the
respondent does not provide a payment schedule to the claimant—
(i) within the time required by the relevant construction contract; or
(ii) within
15 business days after the payment claim is
served,
whichever time expires earlier,
the respondent becomes liable to pay the claimed amount to the
claimant on the due date for the progress payment to which the payment claim relates.
15—Consequences of not paying claimant where no payment schedule
(1) This
section applies if the respondent—
(a) becomes liable to
pay the claimed amount to the claimant under section 14(4) as a
consequence of having failed to provide a payment
schedule to the claimant within the time allowed by that section; and
(b) fails
to pay the whole or a part of the claimed amount on or before the due date for the progress
payment to which the payment claim relates.
(2) In
those circumstances, the claimant—
(a) may—
(i) recover the unpaid portion of the claimed amount from the
respondent, as a debt due to the claimant, in a court of competent
jurisdiction; or
(ii) make
an adjudication application under section 17(1)(b) in relation to the payment claim; and
(b) may
serve notice on the respondent of the claimant's intention to suspend carrying
out construction work (or to suspend supplying related goods and services) under the construction contract.
(3) A notice referred to
in subsection (2)(b) must state that it is made
under this Act.
(4) If
the claimant commences proceedings under subsection (2)(a)(i) to recover the unpaid portion of the claimed amount from
the respondent as a debt—
(a) judgment in favour
of the claimant is not to be given unless the court is satisfied of the
existence of the circumstances referred to in subsection (1); and
(b) the
respondent is not, in those proceedings, entitled—
(i) to bring a cross‑claim against the claimant; or
(ii) to
raise a defence in relation to matters arising under the construction contract.
16—Consequences of not paying claimant in accordance with payment schedule
(1) This
section applies if—
(a) a
claimant serves a payment
claim on a respondent; and
(b) the
respondent provides a payment schedule to the
claimant—
(i) within the time required by the relevant construction contract; or
(ii) within
15 business days after the payment claim is
served,
whichever time expires earlier; and
(c) the
payment schedule indicates a scheduled amount
that the respondent proposes to pay to the claimant; and
(d) the
respondent fails to pay the whole or a part of the scheduled amount to the
claimant on or before the due date for the progress payment to which the payment claim relates.
(2) In
those circumstances, the claimant—
(a) may—
(i) recover the unpaid portion of the scheduled amount from the
respondent, as a debt due to the claimant, in a court of competent
jurisdiction; or
(ii) make
an adjudication application under section 17(1)(a)(ii)
in relation to the payment claim; and
(b) may
serve notice on the respondent of the claimant's intention to suspend carrying
out construction work (or to suspend supplying related goods and services) under the construction
contract.
(3) A notice referred to
in subsection (2)(b) must state that it is made
under this Act.
(4) If
the claimant commences proceedings under subsection (2)(a)(i) to recover the unpaid portion of the claimed amount from the respondent as a debt—
(a) judgment in favour
of the claimant is not to be given unless the court is satisfied of the existence
of the circumstances referred to in subsection (1); and
(b) the
respondent is not, in those proceedings, entitled—
(i) to bring a cross‑claim against the claimant; or
(ii) to
raise a defence in relation to matters arising under the construction contract.
Division 2—Adjudication of disputes
(1) A
claimant may apply for adjudication of a payment claim (an adjudication application)
if—
(a) the
respondent provides a payment
schedule under Division 1 but—
(i) the scheduled amount
indicated in the payment schedule is less than the claimed
amount indicated in the payment claim; or
(ii) the
respondent fails to pay the whole or a part of the scheduled amount to the
claimant by the due date for payment of the amount;
or
(b) the
respondent fails to provide a payment schedule to the claimant under Division 1 and fails to pay the whole or a part of the claimed
amount by the due date for payment of the amount.
(2) An
adjudication application to which subsection (1)(b) applies cannot be made unless—
(a) the claimant has
notified the respondent, within the period of 20 business
days immediately following the due date for payment, of the claimant's
intention to apply for adjudication of the payment claim; and
(b) the
respondent has been given an opportunity to provide a payment schedule to the
claimant within 5 business days after receiving the claimant's notice.
(3) An
adjudication application—
(a) must
be in writing; and
(b) must
be made to an authorised nominating authority chosen by
the claimant; and
(c) in
the case of an application under subsection (1)(a)(i)—must
be made within 15 business days after the claimant receives the payment
schedule; and
(d) in the case of an
application under subsection (1)(a)(ii)—must be made within 20 business
days after the due date for payment; and
(e) in the case of an
application under subsection (1)(b)—must be made within 15 business
days after the end of the 5 day period referred to in
subsection (2)(b); and
(f) must
identify the payment claim and the payment schedule (if any) to which it
relates; and
(g) must
be accompanied by such application fee (if any) as may be determined by the authorised
nominating authority; and
(h) may
contain such submissions relevant to the application that the claimant chooses
to include.
(4) The amount of any
such application fee must not exceed the amount (if any) determined by the
Minister.
(5) A copy of an adjudication
application must be served on the respondent concerned.
(6) It is the duty of an
authorised nominating authority to which an adjudication application is made to
refer the application to an adjudicator (being a person
who is eligible to be an adjudicator as referred to in section 18) as soon
as practicable.
18—Eligibility criteria for adjudicators
(1) A person is eligible to be an adjudicator in relation to a construction
contract—
(a) if
the person is a natural person; and
(b) if
the person has such qualifications, expertise and experience as may be
prescribed by the regulations for the purposes of this section.
(2) A person is not eligible to be an
adjudicator in relation to a particular construction contract—
(a) if
the person is a party to the contract; or
(b) if
either or both of the parties have nominated the person to be an adjudicator in
relation to the contract; or
(c) in
such circumstances as may be prescribed by regulation for the purposes of this
section.
(1) If an authorised nominating authority refers an adjudication application to an adjudicator,
the adjudicator may accept the adjudication application by causing notice of
acceptance to be served on the claimant and the respondent.
(2) On accepting an adjudication
application, the adjudicator is taken to have been appointed to determine the
application.
(1) Subject
to subsection (3), the respondent may lodge with
the adjudicator a response to the claimant's
adjudication application (the adjudication
response) at any time within—
(a) 5 business days after receiving a copy of the application;
or
(b) 2 business days
after receiving notice of an adjudicator's acceptance of the application,
whichever time expires later.
(2) The
adjudication response—
(a) must
be in writing; and
(b) must
identify the adjudication application to which it relates; and
(c) may
contain any submissions relevant to the response that the respondent chooses to
include.
(3) The respondent may
lodge an adjudication response only if the respondent has provided a payment schedule to the claimant within the time
specified in section 14(4) or 17(2)(b).
(4) The respondent
cannot include in the adjudication response reasons
for withholding payment unless those reasons have already been included in the
payment schedule provided to the claimant.
(5) A copy of the adjudication
response must be served on the claimant.
(1) An adjudicator
is not to determine an adjudication application until
after the end of the period within which the respondent
may lodge an adjudication response.
(2) An adjudicator is
not to consider an adjudication response unless it was made before the end of
the period within which the respondent may lodge the response.
(3) Subject
to subsections (1) and (2), an adjudicator is to determine an adjudication
application as expeditiously as possible and, in any case—
(a) within
10 business days after—
(i) the date on which an adjudication response is lodged with
the adjudicator; or
(ii) if an adjudication
response is not lodged with the adjudicator on or before the last date on which
the response may be lodged with the adjudicator under section 20(1)—that
date; or
(iii) if
the respondent is not entitled under section 20 to
lodge an adjudication response—the date on which the respondent receives a copy
of the adjudication application; or
(b) within
any further time that the claimant and the respondent
may agree.
(4) For
the purposes of proceedings conducted to determine an adjudication application,
an adjudicator—
(a) may
request further written submissions from either party and must give the other
party an opportunity to comment on those submissions; and
(b) may
set deadlines for further submissions and comments by the parties; and
(c) may
call a conference of the parties; and
(d) may
carry out an inspection of any matter to which the claim relates.
(5) If any such
conference is called, it is to be conducted informally and the parties are not
entitled to legal representation.
(6) The adjudicator's
power to determine an application is not affected by the failure of either or
both of the parties to make a submission or comment within time or to comply
with the adjudicator's call for a conference of the parties.
22—Adjudicator's determination
(1) An adjudicator is to
determine—
(a) the
amount of the progress payment (if any) to be paid
by the respondent to the claimant
(the adjudicated amount); and
(b) the
date on which any such amount became or becomes payable; and
(c) the
rate of interest payable on any such amount.
(2) In determining an adjudication
application, the adjudicator is to consider the following matters only:
(a) the
provisions of this Act;
(b) the
provisions of the construction contract from which
the application arose;
(c) the payment claim to which the application relates,
together with all submissions (including relevant documentation) that have been
duly made by the claimant in support of the claim;
(d) the
payment schedule (if any) to which the
application relates, together with all submissions (including relevant
documentation) that have been duly made by the respondent in support of the
schedule;
(e) the
results of any inspection carried out by the adjudicator of any matter to which
the claim relates.
(3) The adjudicator's determination must—
(a) be
in writing; and
(b) include
the reasons for the determination (unless the claimant and respondent have both
requested the adjudicator not to include those reasons in the determination).
(4) If, in determining an adjudication
application, an adjudicator has, in accordance with section 10,
determined—
(a) the
value of construction work carried out under a construction
contract; or
(b) the
value of related goods and services supplied under a construction
contract,
the
adjudicator (or any other adjudicator) is, in any subsequent adjudication
application that involves the determination of the value of that work or those
goods and services, to give the work (or the goods and services) the same value
as that previously determined unless the claimant or respondent satisfies the
adjudicator concerned that the value of the work (or the goods and services)
has changed since the previous determination.
(5) If the adjudicator's determination
contains—
(a) a
clerical mistake; or
(b) an
error arising from an accidental slip or omission; or
(c) a
material miscalculation of figures or a material mistake in the description of
a person, thing or matter referred to in the determination; or
(d) a
defect of form,
the adjudicator may, on the adjudicator's own initiative or on the
application of the claimant or the respondent, correct the determination.
23—Respondent required to pay adjudicated amount
(1) In
this section—
relevant
date means—
(a) the
date occurring 5 business days after the date on
which the adjudicator's determination is served on the respondent concerned; or
(b) if
the adjudicator determines a later date under section 22(1)(b)—that
later date.
(2) If an adjudicator
determines that a respondent is required to pay an adjudicated
amount, the respondent must pay that amount to the claimant
on or before the relevant date.
24—Consequences of not paying claimant adjudicated amount
(1) If
the respondent fails to pay the whole or a part of the adjudicated amount to the claimant
in accordance with section 23, the claimant may—
(a) request
the authorised nominating authority to whom the adjudication application was made to provide an adjudication certificate under this section; and
(b) serve
notice on the respondent of the claimant’s intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.
(2) A notice under subsection (1)(b) must state that it is made under this Act.
(3) An
adjudication certificate must state that it is made under this Act and specify
the following matters:
(a) the
name of the claimant;
(b) the
name of the respondent who is liable to pay the adjudicated amount;
(c) the
adjudicated amount;
(d) the
date on which payment of the adjudicated amount was due to be paid to the
claimant.
(4) If
an amount of interest that is due and payable on the adjudicated amount is not
paid by the respondent—
(a) the
claimant may request the authorised nominating authority to specify the amount
of interest payable in the adjudication certificate; and
(b) the
amount so specified is to be added to (and becomes part of) the adjudicated
amount.
(5) If
the claimant has paid the respondent’s share of the adjudication
fees in relation to the adjudication but has not been reimbursed by the
respondent for that amount (the unpaid share)—
(a) the
claimant may request the authorised nominating authority to specify the unpaid
share in the adjudication certificate; and
(b) the
amount so specified is to be added to (and becomes part of) the adjudicated
amount.
25—Filing of adjudication certificate or costs certificate as judgment debt
(1) An adjudication certificate may be filed as a judgment for
a debt in a court of competent jurisdiction and is enforceable accordingly.
(2) An adjudication
certificate cannot be filed under this section unless it is accompanied by an
affidavit by the claimant stating that the whole or a
part of the adjudicated amount has not been paid
at the time the certificate is filed.
(3) If the affidavit
indicates that part of the adjudicated amount has been paid, the judgment is
for the unpaid part of that amount only.
(4) If
the respondent commences proceedings to have the
judgment set aside, the respondent—
(a) is
not, in those proceedings, entitled—
(i) to bring a cross‑claim against the claimant; or
(ii) to
raise a defence in relation to matters arising under the construction contract; or
(iii) to
challenge the adjudicator’s determination; and
(b) is
required to pay into the court as security the unpaid portion of the adjudicated
amount pending the final determination of those proceedings.
26—Claimant may make new application in certain circumstances
(1) This section applies if—
(a) a
claimant fails to receive an adjudicator's
notice of acceptance of an adjudication application
within 4 business days after the application is
made; or
(b) an
adjudicator who accepts an adjudication application fails to determine the
application within the time allowed by section 21(3);
or
(c) an
adjudicator who accepts an adjudication application notifies the claimant and the
respondent that he or she has withdrawn from the
adjudication.
(2) In either of the circumstances specified in
subsection (1)(a) or (b), the claimant—
(a) may
withdraw the application, by notice in writing served on the adjudicator or the
authorised nominating authority to whom the application
was made; and
(b) may
make a new adjudication application under section 17.
(2a) In the circumstances
specified in subsection (1)(c), the application
is discontinued and the claimant may make a new adjudication application under section 17.
(3) Despite section 17(3)(c), (d) and (e), a new adjudication application may be
made at any time within 5 business days after
the claimant—
(a) becomes
entitled to withdraw the previous adjudication application under subsection (2);
or
(b) is
notified by the adjudicator that he or she has withdrawn from the adjudication.
(4) This Division
applies to a new application referred to in this section in the same way as it
applies to an application under section 17.
26A—Claimant may discontinue adjudication
A claimant may withdraw an adjudication
application at any time before the application is determined by notice in
writing served on the respondent, the adjudicator
and the authorised nominating authority to whom the application was made.
Division 3—Claimant's right to suspend construction work
(1) A claimant may suspend the carrying out of construction work (or the supply of related goods and services) under a construction contract if at least 2 business days have passed since the claimant has caused
a notice of intention to do so to be given to the respondent
under section 15, 16 or 24.
(2) The right conferred
by subsection (1) exists until the end of the period of 3 business
days immediately following the date on which the claimant receives payment for
the amount that is payable by the respondent under section 15,
16 or 23(2).
(3) If the claimant, in
exercising the right to suspend the carrying out of construction work or the
supply of related goods and services, incurs loss or expenses as a result of
the removal by the respondent from the contract of a part of the work or
supply, the respondent is liable to pay the claimant the amount of such loss or
expenses.
(4) A claimant who
suspends construction work (or the supply of related goods and services) in
accordance with the right conferred by subsection (1) is not liable for
loss or damage suffered by the respondent, or by a person claiming through the
respondent, as a consequence of the claimant not carrying out that work (or not
supplying those goods and services) during the period of suspension.
28—Nominating authorities
(1) Subject
to the regulations, the Minister—
(a) may,
on application made by any person, authorise the applicant to nominate adjudicators
for the purposes of this Act; and
(b) may
withdraw any authority so given.
(2) The
Minister may—
(a) limit
the number of persons who may, for the time being, be authorised under this
section; and
(b) refuse
an application under subsection (1) if authorising the applicant would
result in any such number being exceeded.
(3) A
person—
(a) whose
application for authority to nominate adjudicators for the purposes of this Act
is refused (otherwise than on the ground referred to in
subsection (2)(b)); or
(b) whose
authority to nominate adjudicators is withdrawn,
may apply to the Administrative and Disciplinary Division of the
District Court for a review of the Minister’s decision to take that action.
(4) An authorised
nominating authority may charge a fee for any service provided by the
authority in connection with an adjudication application
made to the authority.
(5) The amount that may
be charged for such service must not exceed the amount (if any) determined by
the Minister.
(6) The
claimant and respondent are—
(a) jointly
and severally liable to pay such fee; and
(b) each
liable to contribute to the payment of such fee in equal proportions or in such
proportions as the adjudicator to whom the adjudication application is referred
may determine.
(7) An authorised
nominating authority must provide the Minister with such information as may be
requested by the Minister in relation to the activities of the authority under
this Act (including information as to the fees charged by the authority under
this Act).
(1) An
adjudicator is entitled to be paid for adjudicating an adjudication application—
(a) such
amount, by way of fees and expenses, as is agreed between the adjudicator and
the parties to the adjudication, or
(b) if no such amount is
agreed—the hourly rate (if any) prescribed by regulation in addition to
reasonable expenses; or
(c) if no such amount
is agreed and no hourly rate has been prescribed—such amount, by way of fees
and expenses, as is reasonable having regard to the work done and expenses
incurred by the adjudicator.
(2) The claimant and respondent are
jointly and severally liable to pay the adjudicator’s fees and expenses.
(3) The claimant and
respondent are each liable to contribute to the payment of the adjudicator’s
fees and expenses in equal proportions or in such proportions as the
adjudicator may determine.
(4) An adjudicator is not
entitled to be paid fees or expenses in connection with the adjudication of an adjudication
application if he or she fails to make a decision on the application (otherwise
than because the application is withdrawn or the dispute between the claimant
and respondent is resolved) within the time allowed by section 21(3).
(5) Subsection (4)
does not apply—
(a) in
circumstances in which an adjudicator refuses to communicate his or her
decision on an adjudication application until his or her fees and expenses are
paid; or
(b) in
such other circumstances as may be prescribed for the purposes of this section.
30—Protection from liability for adjudicators and authorised nominating authorities
(1) An
adjudicator is not personally liable for anything done
or omitted to be done in good faith—
(a) in
exercising the adjudicator's functions under this Act; or
(b) in
the reasonable belief that the thing was done or omitted to be done in the
exercise of the adjudicator's functions under this Act.
(2) No
action lies against an authorised nominating authority
or any other person with respect to anything done or omitted to be done by the authorised
nominating authority in good faith—
(a) in
exercising the nominating authority’s functions under this Act; or
(b) in
the reasonable belief that the thing was done or omitted to be done in the
exercise of the nominating authority’s functions under this Act.
31—Effect of Part on civil proceedings
(1) Subject
to section 32, nothing in this Part affects any right
that a party to a construction contract—
(a) may
have under the contract; or
(b) may
have under Part 2 in respect of the contract; or
(c) may
have apart from this Act in respect of anything done or omitted to be done
under the contract.
(2) Nothing done under or
for the purposes of this Part affects any civil proceedings arising under a construction
contract, whether under this Part or otherwise, except as provided by
subsection (3).
(3) In
proceedings before a court or tribunal in relation to a matter arising under a construction
contract, the court or tribunal—
(a) must allow for an
amount paid to a party to the contract under or for the purposes of this Part
in any order or award it makes in those proceedings; and
(b) may make such orders
as it considers appropriate for the restitution of any amount so paid, and such
other orders as it considers appropriate, having regard to its decision in
those proceedings.
(1) The provisions of
this Act have effect despite any provision to the contrary in any contract.
(2) A
provision of an agreement, whether in writing or not—
(a) under which the
operation of this Act is, or is purported to be, excluded, modified or
restricted, or that has the effect of excluding, modifying or restricting the
operation of this Act; or
(b) that
may reasonably be construed as an attempt to deter a person from taking action
under this Act,
is void.
(1) A
notice that by or under this Act is authorised or required to be served on a
person may be served on the person—
(a) by
delivering it to the person personally; or
(b) by
lodging it during normal office hours at the person’s ordinary place of
business; or
(c) by
sending it by post or fax addressed to the person’s ordinary place of business;
or
(d) in
such other manner as may be prescribed by the regulations for the purposes of
this section; or
(e) in
such other manner as may be provided under the construction
contract concerned.
(2) Service of a notice
that is sent to a person’s ordinary place of business, as referred to in
subsection (1)(c), is taken to have been effected
when the notice is received at that place.
(3) The provisions of
this section are in addition to, and do not limit or exclude, the provisions of
any other law with respect to the service of notices.
(1) The Governor may
make such regulations as are contemplated by, or necessary or expedient for the
purposes of, this Act.
(2) The
regulations may, either unconditionally or subject to conditions, exempt—
(a) a
specified person or class of persons; or
(b) a
specified matter or class of matters,
from the operation of this Act or of specified provisions of this Act.
(3) Regulations
under this Act may—
(a) be
of general application or limited application; or
(b) make
different provision according to the matters or circumstances to which they are
expressed to apply.
(4) The commencement of a
regulation referred to in section 5, 6
or 7 does not affect the operation of this Act with respect
to construction work carried out, or related goods and services supplied, under a construction contract entered into before that
commencement.
(1) The Minister is to
review this Act to determine whether the policy objectives of the Act remain
valid and whether the terms of the Act remain appropriate for securing those
objectives.
(2) The review is to be
undertaken as soon as possible after the period of 3 years from the date
on which this Act comes into operation.
(3) A report on the
outcome of the review is to be tabled in each House of Parliament within
3 months after the end of the period of 3 years.
Schedule
1—Related amendment and transitional provision
Part
1—Preliminary
In
this Schedule, a provision under a heading referring to the amendment of a
specified Act amends the Act so specified.
Part
2—Amendment of Building
Work Contractors Act 1995
2—Amendment of section 30—Payments under or in relation to domestic building work contracts
(1) Section 30(1)—delete
"the payment"
(2) Section
30(1)(a)—before "constitutes" insert:
the payment
(3) Section
30(1)—after paragraph (a) insert:
(ab) the person is entitled to the payment under
the Building and Construction Industry Security of Payment Act 2009; or
(4) Section
30(1)(b)—before "is of a" insert:
the payment
(5) Section
30(2)—delete "paragraph (a) or (b)" and substitute:
paragraph (a), (ab)
or (b)
(6) Section
30(3)—delete "unless the building work contractor has requested the
payment by notice in writing given to the building owner or an agent authorised
to act on behalf of the building owner." and substitute:
unless—
(a) the building work
contractor has requested the payment by notice in writing given to the building
owner or an agent authorised to act on behalf of the building owner; or
(b) the
domestic building work contract is a contract to which the Building and
Construction Industry Security of Payment Act 2009 applies (in which case
the provisions of that Act relating to progress payments apply).
Part 3—Amendment of Commercial
Arbitration and Industrial Referral Agreements Act 1986
3—Amendment of section 3—Application provisions
Section 3—after subsection
(9) insert:
(9a) Nothing in this Act
affects the operation of Part 3 of the Building and Construction
Industry Security of Payment Act 2009.
Part
4—Transitional provision
This Act does not apply to a construction contract entered into before the commencement of this Act.