Fenwick Elliott Grace Legal Notes
The law of mitigation and constructive acceleration
The American Principle of Constructive Acceleration
It is well known that, in the United States, there is a doctrine of
constructive acceleration. To cut a long story short, the position
there is that if an employer causes delay but refuses to grant an
extension of time for it, and the contractor accelerates to win back
the lost time, the refusal of the employer or his certifier is treated
as a constructive instruction to accelerate, for which the contractor
is entitled to compensation under the contract.
The principle has been applied in Canada (see eg
Morrison Knudsen v V
British Columbia Hydro (No 2) (1978) 85 DLR (3d) 186 (BC
Ct App), but what is the position in Australia?
The Tension
There is a tension between two conflicting considerations here:
1. On the one hand, it offends against
the principle that no one should be permitted to benefit from his own
wrong, and some mechanism thus recommends itself for ensuring that the
employer does not benefit from a wrongful failure to grant an
extension of time that is due, conversely
2. If a contractual provision for delay damages does not
contain any express mechanism for payment for acceleration in these
circumstances, it offends against ordinary principles for the
implication of terms to invent one. Thus Hudson criticises the doctrine
as fictitious. And, at any rate in jurisdictions where
Pacific v Baxter
holds sway, the employer is not to be treated as vicariously liable in
damages for the certification failures of the certifier.
Disruption Clauses
UK contracts typically contain clauses whereby the contractor is
entitled to compensation under eh contract for disruption that might
or might not delay the contract completion. These clauses will
typically allow the contractor to recover acceleration costs under the
contract where he has accelerated to overcome an employer-caused
delay. There is thus no need for a doctrine of constructive
acceleration.
AS4000
The Australian form AS4000 does not contain a disruption clause. The
contractor is entitled to delay damages under clause 34.9 only for
"every day the subject of an EOT for a compensable cause...". So, prima
facie, no delay, no damages under the contract. However, Clause 20 of
AS4000 obliges the employer (Principal) to ensure that the certifier
(Supervisor) fulfills all aspects of the his role and functions
reasonably and in good faith.
Further,
Pacific v Baxter does not hold the same sway in Australia as
it might in England. The position is neatly set out
in
Multiplex
Constructions Pty Ltd v SOR Pty Ltd and Woodhead International Pty Ltd
[2000] SASC 414 by Duggan J:
Mr
Dal Cin submitted that the principal in a construction contract would
not be liable for the negligence of a superintendent acting in his
capacity as a certifier. He referred to Hudson's Building and
Engineering Contracts (11th ed) Vol 1 para6-097. The learned author of
Hudson relies on Pacific Associates v Baxter [1990] 1 QB 993 for this
proposition. In my view this is stating the matter too broadly. In P
& E Phontos Pty Ltd v McConnell Smith & Johnson Pty Ltd
(1993)
9 BCL 259 Cole J expressed the view that the decision in Pacific
Associates turned on the particular circumstances of that case and that
the court should approach each case in which negligence is alleged by
considering the particular circumstances said to establish a duty of
care. Cole J was of the view that in the imprecise area of the law of
negligence the burden upon an applicant seeking to strike out a summons
is greater because of the developing nature of the concept of duty of
care. That statement is just as true now as it was when it was made by
Cole J in 1993. (cf Perre & Ors v Apand Pty Ltd (1999) 198 CLR
180). Nor do I agree with Mr Dal Cin's argument that the contractual
relationship necessarily excludes the existence of a duty of care. In
my view the pleadings disclose a reasonably arguable cause of action
against SOR based on breach of duty of care.
and accordingly there may be a parallel liability in tort.
The Damages
And so, if the certifier (Superintendent) unreasonably or negligently
fails to grant an extension of time, the employer may be liable in
damages. But it there a sufficient causative link between
the breach (delay/failure in certification) and the loss (the cost of
acceleration)?
The 3 Rules of Mitigation
The first rule of mitigation is well known;
the others less so.
The point can readily be illustrated by an example. A plumber fails to
seal a pipe, which starts to leak. The owner sees the leak.
He knows or ought to know that if he does nothing to catch
the drips, the leaked water will bring his ceiling down. The three
rules apply as follows:
Rule 1: The owner must put a bucket under
the leak.
Rule 2: If he does so, such
that the ceiling is not damaged, he cannot recover the cost of
repairing the ceiling that would have arisen but for placement of the bucket.
Rule 3: If he had to go out and buy a
bucket from the corner shop, he can recover the cost of the bucket.
Under this head, he can recover the cost of a reasonable attempt to
mitigate, regardless of whether the attempt proves successful; or not.
It is under this third rule - that the innocent party can recover the
cost of reasonable attempts to mitigate (whether they are successful or
not) - that a contractor can probably claim the cost of the acceleration.